|
Construction in modernity is vastly different from construction in
antiquity. The Bible does not mention Noah being sued when he built
the Ark, and evidently he made no claim for flood damage. The pyramids
of ancient Egypt took 20 years to build and necessitated the labor
of 100,000 people, yet no delay of damages suit ensued. Similarly,
there is perhaps no greater example of design defect than the Leaning
Tower of Pisa, but history holds no record of the lawsuit that should
have resulted. Those litigious-absent days evidently are gone forever.
Today, the owner sues the contractor, and vice versa. Contractors and
subcontractors sue each other, and all parties carry insurance to cover
a multitude of liability issues. Each party's respective theories of
entitlement, and a construction law overview, are covered in this section.
Awarding a construction contract to a single contractor is the archetypal
construction project situation. Here, the owner contracts with the
general contractor for the completion of the entire project and the
general contractor, in turn, contracts with various subcontractors
for the completion of various aspects of the project (e.g. electrical,
mechanical and plumbing work). It is the responsibility of the general
contractor to coordinate the activities of the various subcontractors,
and the project is built in accordance with the plans and specifications
provided by the owner.
Contracting construction work typically involves either the direct
hiring of a contractor or competitive bidding among different contractors.
Government contracts differ from nongovernment contracts in that
private sector contracts have few constraints, while public sector
contracts involve extensive regulations imposed by the government.
Private sector construction contracts may either be directly hired
or bid upon. The direct hiring of a contractor is the hiring of a
contractor at the individual's own discretion. Competitive bidding
gives all contractors a chance to bid on the construction contract
and allows the individual to hire the lowest bidder.
Public sector contracts involve competitive bidding. Since the
government is a major employer and is political in nature, there
is an assumption that there may be impropriety and that the government
cannot be trusted to meet and negotiate suitable terms without at
least the appearance of impropriety or special favor. Thus, competitive
bidding serves the dual purpose of safeguarding against favoritism
toward a particular contractor and giving all a fair opportunity
to participate.
In most bidding procedures, there will be a "request for bids," which
is an invitation to construction companies to make bids on a construction
project. (Private owners and governments typically reserve the right
to reject all bidders, usually for skill or reputation in trade.) After
the request for bids, the bidders typically will obtain "bidding
information,"
which includes the drawings or plans for the project, job specifications, the
parties involved, and the proposed contract. Upon receiving the bid documents,
the bidder will submit a "bid proposal"; i.e. the offer (usually irrevocable
for a certain stipulated period of time). Factors considered in accepting a contractor's
bid include: financial ability, reputation, equipment availability, and skill
and expertise. After the lowest bidder's offer is accepted, the hirer (the owner
or public body) makes a formal award of the contract, typically through written
formal notification. If the bidder signs the contract, a binding agreement is
created.
The Illinois Purchasing Act requires competitive bidding in
all public contracts, and all prospective contractors be "qualified bidders" (using considerations
such as quality and serviceability, terms of delivery, and site specifications).The
Act also requires that
"economical procurement practices" shall apply to all purchases and
contracts by or for any State Agency. In other words, the state agency may in
good faith determine that it is more economical to perform the work with its
own employees than to let the contract by competitive bidding. (See Illinois
Section 505/2 et. seq.) Further, Illinois courts have held that a public body
may not draw specifications in its bid request that would permit only one bidder
to qualify for the project, and that all bidders be
"resident contractors" (i.e. licensed to transact business in the
State of Illinois).
Cases that involve fraud or ill repute in contract bidding usually nullify
the contract. For example, if a city or county lacks the statutory authority
to enter into a particular contract, the contract is void and the contractor
may not recover for work performed. Cases that involve bad faith or bribery
are also nullified, with the contractor receiving nothing.
However, accidental bidding discrepancies sometimes occur. The nature of
the bidding process means that bidders sometimes miscalculate their bids. Relief
is typically granted when the mistake was an honest error in mathematics or
a clerical error but the courts have refused to grant relief for errors of
judgment. The Illinois courts also have allowed rescission of contracts when
enforcement of the contract would be unconscionable or when unforeseen circumstances
render the contract unenforceable. In cases of unconscionability, courts either
will grant relief to the bidder, a refund of the bid deposit, or an action
for rescission of the contract.
When the bidding contract involves a prime contractor and a subcontractor,
a subcontractor generally may not hold the prime contractor liable for the
prime contractor's use of the subcontractor's bid unless there was an agreement
stating otherwise. Thus, if a prime contractor uses a subcontractor's bid,
the prime is not compelled to use the subcontractor if the prime is awarded
the project; similarly, a prime contractor may not hold a subcontractor liable
for the subcontractor's bid unless there was substantial reliance on this bid
by the prime contractor in making his or her bid, in which case the court may
impose the doctrine of promissory estoppel and hold the subcontractor liable
for its bid. Further, Illinois law requires that any person or business entity
who enters into a contract for consultant swerves with a State agency shall
state in the contract whether the services of a subcontractor will be utilized,
along with the subcontractors' names, addresses, and fees charged thereby.
There are three major methods of payment in construction contracts: lump sum,
cost-plus, and unit price. Partial payments are typically made to the contractor
in incremental sums during the project, with contract clauses usually providing
for a time or condition precedent for payment.
Lump sum payments are found in fixed-price contracts and provide that upon
completion of a contract, the contractor is paid the amount due. Cost-plus
contracts provide that a contractor will be paid for all costs, plus a percentage
or fixed amount for profit and overhead. The unit price method is used when
the same project will be completed several times; e.g., a development project
where many houses are being built. A unit price contract would provide a certain
amount of houses and a certain price per house, and the contractor would be
paid in increments upon the completion of each house.
Once the payment method is determined, the next step is to calculate the
terms and conditions for payment. A relic of the English legal system under
Oliver Cromwell, performance contracts have typically required performance
of all labor before any payment is requiredabsent an agreement to the contrary.
However, progress payments are instituted in most construction contracts to
provide relief to ease the contractor's financial burden of having to finance
the entire projectincluding labor, supplies, and credituntil its full completion.
Progress payments are partial payments for work completed at a particular stage
of the project and ameliorate the problems of payment collection.
In construction projects, performance may be less than perfect and strict compliance
with contractual provisions may not be literal. In these cases, the Illinois
courts have held that where there is substantial performance, the contractor
is entitled to recover the contract price, less costs of remedying the minor
defect or omission or reimbursement to the owner for the diminished value. (In
Florida, if the contractors have not substantially performed their duties, then
the contractor, under a contractual restitution principle, may still recover
for work completed.) Under this theory, the contractor is paid the value of any
benefit conferred upon the owner by the contractor's performance.
Contractual undertakings require the implementation of various clauses to protect
owner, contractor, and subcontractor against ambiguities or contractual malfeasance.
Since there are as many "standard" construction contracts as there
are contractors and subcontractors, generalizations concerning standard contracts
can be perilously misleading. However, the Association of General Contractors
has provided "neutral"
contract provisions that construction contracts should contain to prevent potential
problems.
-
Unexpected delays or scheduling problems can require last-minute modifications
in the work assignments of subcontractors and should be considered when forming
the contract. Changes clauses are a standard in virtually every construction
contract because they allow modifications in the design, specifications,
and timing of a project as the desire or need for such modification becomes
apparent during construction. Typically, the owner may initiate these changes,
or must approve changes which the contractor indicates are necessary. The
owner is then responsible for the additional costs associated with these
changes. This clause allows changes to be made in the construction of the
project without completely stopping work on the project altogether, and is
normally construed to require prompt performance on the part of the contractor
and subcontractor, with expedited consideration from the owner because of
any dispute involving the terms of the change.
-
Before work on the project begins, each party should
be clear as to its duties and obligations; i.e., the work and the costs
involved. This is contained in the Scope of Work Clause, which defines
the labor, materials, services and costs involved in the project. Contractors
should be careful to avoid dragnet or all-inclusive clauses with boilerplate
terms like "all
work necessary to complete said project," "all related items" and "all
work normally undertaken in this type of trade." Indeed, since the
scope of work is often defined in various documents, each Scope of Work
Clause should be "identified and incorporated" as such into
the general agreement.
-
Virtually all contracts contain a clause that allows
incorporation of a clause into the general agreement; in construction
contracts, these are typically called Flow-Down and Flow-Up Clauses
(also known as "Conduit
Clauses").
A Flow-Down Clause provides that all duties and obligations the contractor
owes the owner are owed by the subcontractor as well. Similarly, the
Flow-Up Clause ensures the owner's obligations and duties to the contractor
will also be owed to the subcontractor.
-
Illinois (together with Wisconsin, Texas, and Arkansas) statutorily
requires that certain public owners must retain ten percent from the
contractor's pay. Illinois Statute (121/5-409 [1993]) requires partial
payments on contracts let by a county for highway work may be made
as the work progresses, but no payment in excess of 90 % of the value
of the work then completed may be made until 50% of the work has been
completed. However, retention of the 10% may terminate once 50% of
the construction work is completed. Of all states with a statutorily
mandated retention clause, only Illinois has a statute which requires
the retaining of contractor sums in a pure trust account. (There are,
however, states that require the establishment of an escrow account.)
This trust is put into an Illinois bank of the contractor's choice,
is subject to the approval of the State agency, and all interest from
such trust is to be paid to the contractor.
-
Parties should devote attention to Payment Clauses, which set forth
a schedule of payment that is contingent on the general contractor
getting paid before there is any payment to the subcontractor. Further,
Safety Clauses are often standard and require subcontractors to observe
basic safety requirements on the job site. For projects involving
many subcontractors, Scheduling Clauses are often included in each
subcontract to ensure that neither party will incur liability in
the event that a third-party subcontractor's performance is delayed.
Once the contract is executed, it may be modified only if both parties
mutually assent to the modification. Agreement of both parties is
required since the modification is seen as a new contract, and therefore
the contractual requirements of offer, acceptance and consideration
(typically money or another benefit) apply. Illinois courts have
stated that furnishing additional labor and construction project
materials in exchange for more money is adequate consideration. Written
modifications are not required unless the Statute of Frauds or the
contract itself necessitates a writing.
A frequent problem on construction projects is the discovery of a
previously concealed condition that makes the work more difficult,
more expensive, or perhaps impossible to perform. These discoveries
typically result in a need for additional time, contract revisions,
or even rescission of the contract. Therefore, flexibility to make
changes is an important part of construction law. In Illinois, the
two most common types of clauses used to deal with concealed or changed
conditions are the Site Investigation Clause, and the Changed Conditions
Clause.
The Site Investigation Clause allows the contractor to make a
claim for any condition not reasonably discoverable by an investigation
of the site. However, the Site Investigation Clause has proven
to be one of the general contractor's worst enemies. It is often
asserted by the owner as a defense to the contractor's claim for
"extras" since some Illinois courts have ruled that the
contractor "could or should have anticipated the extra from
a reasonable site inspection."
While the Site Investigation Clause is a common construction contract
disclaimer, by far the more common contract disclaimer is the Changed
Conditions Clause.
There are two types of Changed Condition Clauses: the first addresses
the contractor encountering a condition that is at variance with
the conditions already documented in the agreement, and the second
deals with the discovery of conditions or situations that are anomalous
or incongruous with the type of work provided for in the contract.
In Changed Condition Clauses, custom in the trade is often the
standard for recovery, which is typically allowed unless the contractor
knew or should have known of the conditions.
Most construction contracts involve time restraints
and many involve "time
is of the essence"
provisions. However, delays in the completion of a project sometimes
happen, and a delay claim for damages is essentially a claim that
the contract has been breached. However, in contract law, a breach
of contract must be a material breach to file a claim for damages.
Tardiness in completion alone is usually not part of the basic exchange
of values in a construction contract, and thus not a material breach.
Consequently, a construction contract should specify whether damages
are recoverable if one party fails to perform. The "substantial
factor test" is often applied to subcontractors. Here, courts
will hold subcontractors liable for damages cause by delayeven though
other subcontractors may contribute tot he delayif the subcontractors
conduct is a substantial factor in the project's delay.
Three kinds of clauses are generally used to ensure indemnification
in the event of a delay: Actual Damages Clauses, Liquidated Damages
Clauses, and No-Damages-For-Delay Clauses. Actual Damages Clauses
provide that a delay is a breach of the contract, and that the
breaching party must pay money damages equal to the amount of damages
suffered. Liquidated damages set an agreed-upon amount for damages
to be paid in the event of a breach. No-Damages Clauses contractually
limit liability to provide no relief in the event of a delay.
A mechanic's lien is a security device by which unpaid contractors,
subcontractors, and suppliers may enforce payment for services and
materials through the lien process. To acquire a mechanic's lien,
a claimant must fall into one of state-protected classes of lienors,
including: contractors, subcontractors, suppliers, laborers and mechanics.
Mechanic's liens are typically statutory, so claimants must observe
state regulations in strict obeisance. Substantial performance and
proof of use of the materials into the construction project are required
before the lien will attach. In most states, evidence that materials
were delivered to the site is sufficient proof that materials were
used in the construction project. However, once a lien is attached
to the property, the courts will liberally interpret the lien requirements
in order to accomplish the parties' objectives in completion of the
project. In the event that the parties' objectives (presumably, completion
of the project) cannot be met, courts have allowed the claimant to
use the remedy of repossession. Proceedings for repossession are
quite similar to proceedings used to foreclose a mortgage, and are
subject to time constraints imposed by either the mechanic's lien
statute itself, or by the statute of limitations.
Defenses to mechanic's liens are found in common and statutory
law. An owner may defeat a claim for a mechanic's lien by proving
the lienor's failure to comply with the statutory requirements
(failure to prove that the materials in dispute were used in the
construction project, for example), or by proving contractual provisions
showing waiver of the lien or lien preclusionprovided the language
of the waiver or preclusion is clear and unambiguous. Further,
if the holder of the lien gave false, misleading, or inflated price
information, any mechanic's lien will be rendered null and void.
Illinois law provides that the prevailing party in a mechanic's
lien foreclosure will recover reasonable attorney's fees in an
amount to be determined by the court. However, once the U.S. Supreme
Court held that public property was exempt from mechanic's liens,
surety bonds for construction projects became an established practice
in construction law.
Surety bonds date back to Biblical times, and were
commonly used when contracts were generally non-enforceable, so
merchants could protect themselves in commercial transactions.
Furnishing contractor's bonds began in the late 1800's to provide
owners with protection against contractor's defaults, and laborers
and material providers with protection against nonpayment. Today,
the "Miller Act" (40,
United States Cod, section 270) requires contractors to furnish payment
and performance bonds as a conditions to the award of any substantial
public federal contract. Similarly, all states have "Little
Miller Acts" which require the same bond coverage for all public
state contracts. Owners, concerned with the threat of mechanic's
liens, sought the same kind of bond protection enjoyed by the public
sector. Hence, the use of private bonds came into general use. Today,
the mechanics lien and the surety bond together furnish the foundation
for the credit structure of one of the United States' largest industries,
the construction business.
In construction contracts, owners typically will require the
contractor to provide the owner with a private payment bond. Private
payment bonds protect the owner from mechanic's liens from various
subcontractors in the event of their nonpayment by the contractor.
The bond's surety either will pay to the extent of the amount specified
in the bond (provided the claimant furnishes the requisite notices
to the debtor) or will effect performance of the work (i.e. the
surety guarantees to the owner faithful performance of the underlying
contract between the owner and the contractor).
An owner's or general contractor's liability in construction projects
is dependent on their duty to provide a safe work environment. For
construction work that is inherently dangerous, owners and general
contractors have been held strictly liable for injuries incurred
on-site, unless special precautions are undertaken by the owner or
general contractor. Illinois has enacted the Structural Work Act
(IL Statutes section 150/1), which was enacted to provide workers
in extra-hazardous occupations a relatively safe place to work. In
order to establish a cause of action for violation of the Act, the
claimant must show that the injury was one designed to be protected
from by the Act, those in charge of the work willfully violated the
Act, and that violation of the Act proximately caused plaintiff's
injury. Significantly, the party (owner or general contractor) in
charge of the claimant's work is immune from tort liability under
the Structural Work Act, pursuant to Illinois' worker's compensation
laws, since the supreme court does not consider worker's compensation
benefits to be a collateral source of recovery.
Finance creativity in construction projects has resulted in lenders
becoming more involved in the construction process, thus expanding
the boundaries of lender liability. Developers who wish to obtain
a construction loan typically need to present a loan commitment to
the construction lender for approval. Upon approval of the loan,
the relevant parties agree that when the construction project is
completed, the permanent lender (the owner's bank) thereupon will
purchase the construction loan from the construction lender (typically
a commercial bank that specializes in short-term construction loans).
When lenders participate with developers in joint ventures, courts
consistently have found lenders liable to third-party purchasers
for construction defects. A joint venture typically exists if four
elements are found: (1) a common purpose, (2) joint control or
right of control, (3) joint proprietary interest, and (4) mutual
sharing of profits and losses. If the existence of each element
is proven by the claimant, the lender will be liable to third-party
purchasers for construction defects.
Most courts do not hold lenders liable for negligence claims
on construction projects. Construction lenders periodically may
inspect the site to monitor project progress, and often extract
a fee for doing so. If an inspection fee is extracted from the
construction loan, this does not give rise to the requisite duty
standard required for a negligence action. However, if the lender
assumes title of the project or becomes more than a lender by holding
itself out to be the developer or owner to purchasers, the lender
will then be held liable for completion of the project to the extent
of the express representations made to the buyer. Further, the
assuming lender may be liable for construction defects and breach
of any warranties due to these defects.
In large construction projects (and some smaller jobs), design professionals
such as architects or engineers provide blueprints and plans for
more sophisticated design projects like condominiums, office buildings,
shopping malls, or even homes. Although form agreements in construction
contracts have become customary, ignorance of their legal significance
can be very problematic for contractors and design professionals
alike. If design professionals fail to perform their duties properly,
they can be held liable for breach of contract, negligence, failure
to disclose a material or latent defect, or other actions if the
court finds their conduct subjects the architect or engineer to strict
liability.
The construction contract lists the duties of the design professionals,
and if these professionals fail to perform their duties, the owner
may sue for breach of contract. Damages for breach are limited
to an amount that is reasonably foreseeable at the time the contract
was made or to an amount that is a natural consequence of the breach.
Design professionals acting in their professional capacity are
held to a higher standard of care that is consistent with their
higher degree of knowledge and skill. Therefore, a design professional
whose performance does not meet the reasonable standard of care
of similar professionals with similar skills will be found liable
for negligence. This negligence standard applies to the professional's
drawings or plans, preparation, inspections, and supervision of
relevant personnel. If it is reasonably foreseeable that the negligent
conduct will result in injury, the design professional may be liable
to third parties for sustained injuries. However, these third parties
are only owed a duty of care if they are within a class of persons
who the design professional could reasonably foresee might be damaged
or injured as a result of the negligence. This class of persons
includes project owners, subcontractors, suppliers, contractors,
sureties, lenders, and injured construction workers. However, negligence
claims or tort actions generally do not allow recovery for solely
economic losses. To recover economic losses in a tort action, the
design professional must be held liable under a standard called
strict liability.
Strict liability is a tort concept in which one is found liable
regardless of fault, contributory negligence, or anything else
that normally absolves persons of liability. Courts have been very
reluctant to impose strict liability on design professionals as
it is usually impossible to differentiate between a construction
defect and a design defect because they are often closely intertwined.
However, none of these standards of liability are designed to
assure conformity with the plans or specifications by the design
professional. No construction contract guarantees or implies perfection
in either plans or results, and design professionalsabsent strict
liabilityare liable only for failure to exercise reasonable skill
in preparation and execution of the plans. Similarly, contractors
are not responsible for defects in the plans or specifications
given to them by design professionals hired as independent contractors.
Design professionals may need to hire consultants from various disciplines
for construction projects. Consultants such as structural, civil,
or mechanical engineers or electrical experts working on construction
projects at the behest of the architect or engineer (as opposed to
being hired by the owner) are considered independent contractors.
According to the federal courts and Restatement (Second) of Agency,
$220, in determining whether a consultant is an independent contractor
or an employee the court will consider: the extent of control that
the design professional may exercise over the details of the work;
the terms of the agreement; the method of payment; the degree of
skill required for the job; previous dealings between the parties;
and previous scopes of employment of the consultant. If the relationship
is determined to be employer/employee, then the tort doctrine of
respondeat superior applies, making the employer responsible for
the torts committed by the employee (if committed within the scope
of employment).
A design professional acting as an independent contractor is
generally not liable for the acts of the independent contractor,
since the duties were delegated to this contractor in a consultant
capacity. However, sometimes ordinances or building codes will
create non-delegable duties of compliance, such as fire codes regulating
a project's design. In these cases, independent contractors may
be liable for injuries sustained by those within the class of people
intended to be protected by the ordinance.
Construction agreements commonly provide details on who is responsible
for bearing the responsibility for accidents on the site. Florida
Statutory law requires comprehensive general liability insurance
($489.115) and workers' compensation insurance ($440 et. seq.). Builder's
risk insurance and professional liability insurance are standard
in most construction contracts. Most contracts contain indemnity
provisions to determine who will bear the risk of loss should an
on-site accident occur, and the purchaser of the insurance should
be required to furnish a copy of the policy to the other party.
Comprehensive General Liability Insurance protects contractors against
claims brought against them because of occurrences in privity with
the contractor's work, and coverage typically extends only to property
damage and bodily injury. Business risks such as claims for defective
work or structure defects are covered by other policies; and builder's
risk insurance protects against loss to buildings during construction,
alteration or repair. (This coverage is usually voided once the work
is done or once the project is occupied.) Professional liability
insurance is carried by professional designers to protect against
losses relating to their work on the project or to cover claims made
against them by third parties. Owners are increasingly requiring
design professionals to carry liability insurance since owners may
have a claim against the design professional for losses relating
to the project or for satisfaction of claims to third parties.
Usually a Comprehensive General Liability Insurance policy excludes
coverage for workers' compensation claims, unemployment compensation,
or disability benefits. This risk insurance is obtained under separate
policies, and in every state, workers' compensation coverage is required
for all employers. General contractors are often required by the
owner to procure workers' compensation for subcontractors as well
as employees. However, it is customary for general contractors to
fulfill this duty by requiring their subcontractors to procure the
coverage themselves, since worker's compensation insurance for employees
and subcontractors would be very expensive. If subcontractors do
not obtain this coverage, despite their obligation, the general contractor
bears responsibility to procure this insurance coverage if the contractor
hires the subcontractor. In contrast, the contractor is generally
not obligated to provide coverage for vendors or lessors of equipment.
Further, if the worker is an independent contractor instead of a
subcontractor, general contractors are not obligated to provide workers'
compensation coverage. Courts often use a two-pronged test to determine
whether the worker is a subcontractor or an independent contractor:
1) Is there a subletting of the contractor's work? and 2) Does the
contractor have control over the worker? If an employee files a workers'
compensation claim and wins, then that is the sole recovery for the
employee. However, it is possible under certain conditions that an
independent contractor may file a separate claim against an employee
or subcontractor on the site.
Breach of construction contracts entails many things: the owner's
failing to make periodic payments, failure to cooperate by either
party, unforeseen conditions that render completion impractical or
impossible, project abandonment, or a general failure to fulfill
the contractual obligations. If conditions occur that make performance
by one party impossible, then a party not at fault may, in good faith,
terminate the contract for cause without fear of damages. However,
these terminations must not be arbitrary or unreasonable or they
will constitute wrongful termination. Wrongful termination is a breach
of contract for which the injured party may collect compensatory
damages, which typically amount to lost profits and a reasonable
calculation of labor and materials involved in the partial completion
of the project.
Most construction contracts contain either a Time-Is-Of-The-Essence
Clause, a Damages-For-Delay Clause, or a No-Damages-For-Delay Clause.
These clauses typically insulate, protect, or prevent one of the
parties from having to breach the contract in the event of nonperformances,
such as unforeseen circumstances or impractical occurrences. More
importantly, they provide remedies, or a limitation of remedies,
in the event of a breach. A Time-Is-Of-The-Essence Clause will provide
a fixed time for performance, with a remedy if completion exceeds
this time allotment. A Damages-For-Delay Clause provides remedies
for the contractor in the event of noncooperation from the owner,
or contingencies that interfere with a timely performance. No-Damages-For-Delay
Clauses protect the owner from breach assessments in the event of
certain listed occurrences, such as financing problems or construction
access easements. This clause will exclude damages against the owner
for delay of performance.
Introduction to Construction Law, Steven M. Siegfried, ALI/ABA
Continuing Legal Education, Philadelphia, PA (1987).
Handbook of Modern Construction Law, Jeremiah D. Lambert and
Lawrence White, Prentice-Hall, Inc., Englewood Cliffs, NJ (1982).
|
 |